SAAP 2016-20 Guntakul

Name of the Project
DETAILED PROJECT REPORT FOR SEWAGE TREATMENT PLANT AND SEPTAGE MANAGEMENT FOR GUNTAKAL MUNICIPAL CORPORATION – 8 MLD STP AND INLET WORKS WITH PUMPING STATION
Name of the Agency
M/s. Eco Protection Engineers Pvt. Ltd.,
SAAP Approval Meeting No. & Date by SHPSC SAAP Approved Cost
(In Cr.)
Technical Approval Date of DPR by SLTC Administrative Approval of DPR by SHPSC NIT Approved Administrative Sanction Cost (In Cr.)
6
15/03/2017
16.00 06/01/2017 08/02/2017 25/09/2017
Tender Floated On Last Date of receipt of Tender Tender Type IBM / ECV Value % of Tender
Yes 31/10/2017 EPC 18.80 4.500
Contract Awarded Cost
(In Cr.)
Contract Awarded On Contract Period (Months) Completion Date Remarks
19.64 22/12/2017 18 21/06/2019 SAAP: 2016-20 Sewage and Septage Plant.  Project: SEWAGE TREATMENT PLANT AND SEPTAGE MANAGEMENT Project cost - 26.71 crores (Estimate cost)  Agency: Eco protection Engineers pvt Ltd. Contract agreement date: 07-02-2018,  Project completion: 15 months Completion date: 07-05-2019 Status: STP work not established in Guntakal due to land acquisition in progress. Land not handover to the contractor so work not started... Designs not prepared and not submitted. Issue : Land acquisition issue. Letter issued from RDO office to GMC Commissioner regarding Deposit of Cost of Land Acquisition requested. Date: 20-01-2018 Letter No: RC.NO.D1-LA/2814/2017.  STP Deposit of Cost of Land Acquisition requested CR is approved in a Council meeting.  Date: 30-04-2018. CR NO: 205. Letter issued from District Collector office to GMC Commissioner regarding conducting preliminary enquiry U/R 4 of LARR Rules, 2014. Letter No:Rc.No.G1/3583/2018. DT: 04-06-2018, Letter issued from GMC Commissioner to District Collector regarding Under Private Negotiations purposes. Letter No: Roc.No.673/2.17/G1, DT: 08-06-2018. Letter issued from PH sub-division DEE Sir to GMC commissioner sir regarding under construction of 8 MLD STP feasibility report purpose. Letter NO:12M; DT: 16-07-2018. Requested letter issued from GMC (GTL) Commissioner sir to RDO office (ATP) regarding compulsory land Acquisition purpose. Roc NO: 673/2017/G1; DT: 17-07-2018. Land Acquisition under process.

Project In-Charge Official Details

Name: Mr. N.Eswaraiah
Designation: Municipal Engineer
Email: guntakalmunicipality@gmail.com
Phone: +919849907414

Project Components

News & Updates
  • 7th SHPSC Minutes of Meeting held on 10.05.2017

    Download

  • 6th State Level Technical Committee (SLTC) Minutes of Meeting held on 08.05.2017

    Download

  • 6th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 23.03.2017 under AMRUT

    Download

  • 3rd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 06.01.2017 under AMRUT

    Download

  • 2nd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) under AMRUT

    Download

  • Minutes of 12th Meeting of Apex Committee under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) regarding.

    Download

  • SAAP 2016-17 Documents

    State Annual Action Plan (SAAP) (FY 2016-17) Andhra PradeshDownload