Government of Andhra Pradesh Government of
Andhra Pradesh, India
Andhra Pradesh Urban Finance and Infrastructure Development Corporation (APUFIDC) Andhra Pradesh Urban Finance and
Infrastructure Development Corporation
Municipal Administration & Urban Development (MA & UD)

SAAP 2015-16 Guntakul

Name of the Project
Electronic Total Station (ETS) Survey, Investigation, Design, Build, Commissioning of Providing Water supply House Service Connections, Distribution lines, Construction of Filtration Plant and Off-take well cum Raw Water Pump House including supply and fixing of Pump sets in Guntakal Municipality under AMRUT Scheme including O&M for 7 years inclu
Name of the Agency
GPR Infra Pvt.Ltd.
SAAP Approval Meeting No. & Date by SHPSC SAAP Approved Cost
(In Cr.)
Technical Approval Date of DPR by SLTC Administrative Approval of DPR by SHPSC NIT Approved Administrative Sanction Cost (In Cr.)
1
21/09/2015
14.08 11/02/2016 24/03/2016 04/10/2016
Tender Floated On Last Date of receipt of Tender Tender Type IBM / ECV Value % of Tender
Yes 27/09/2016 EPC 14.78 4.920
Contract Awarded Cost
(In Cr.)
Contract Awarded On Contract Period (Months) Completion Date Remarks
15.50 11/08/2017 18 10/02/2019 1) Survey work starting date: 19.09.2017. 2) Revised designs of 5 MLD WTP to be submitted by contractor. 3) Soil samples from the WTP AND OFTAKE WELL cum PUMP HOUSE sites have been collected and testing completed. Designs to be submitted by contractor. 4) 5 MLD Filtration plant flow diagram approved and Detailed Designs under scrutiny. 5) Distribution HDPE Pipes Scrutinized and approved by SE (PH) ,ATP and Total Pipes are procured by Contractor. Work is under progress. 6) Quality of HDPE Pipes testing and Inspection is completed by the Third Party Inspection Agency on Dt:16-12-2017 at Vijaya Polymers India Pvt ltd. and materials are procured by contractor. 7) Detailed Designes submitted to SE (PH) ATP, for 8m Dia off Take well cum pump house at HNSS Canal. Designs under Scrutiny. 8) For House Service Connections testing and Inspection is completed by Third Party Inspection Agency on Dt:26-12- 2017 at kimplas Piping System, Nashik and Materials are procured by Contractor. 9) MDPE pipes testing and inspection completed by Third Party Inspection Agency on Dt:30-12-2017 at Dura Line India Pvt Ltd, Hyderabad and Materials are procured by Contractor. 10) Distribution pipe line designs and drawings approved, Distribution pipe line excavation is stared. 11) Deposit of cost of land acquisition requested letter issued from RDO office to GMC Commissioner. Dt: 24-01-2018. 13) 5 MLD Filtration plant flow diagram and Detailed Structural Designs, Drawings approved by SE (PH) Dt: 07/02/2018. 14) Indiramma colony - I, Proterline to Bharmashala and Prashanthi nagar colony distribution and distribution main line earth work excavation and laying is completed. 15) HSC work starting date: 12.02.2018. Work Status: Agency: M/S.GPR Infra. Letter of acceptance Date: 09-05-2017, Contractor Agreement date: 11-08-2017, Target date of completion: 11-02-2019, (18 months’ completion) 1) Off take well cum Pump house in Hundri Neeva Canal (HNSS) at Guntakal - 8.0m trsdia Status: Concrete work completed upto Roof Slab Further work is in progress. 2) WTP - 5.00MLD Capacity Rapid Gravity Filtration Plant i) 5.00MLD Capacity Rapid Gravity Filtration Plant Status: 5 MLD - WTP designs and drawings by approved by SE (PH) (ATP). DT: 26-11-2018. Excavation in progress DT: 01-12-2018. iI) Chemical house Concrete work completed upto plinth beam, Columns concrete work is completed upto 2nd lift (above plinth beam) and Roof slab shuttering works in progress. iiI) Clariflocculater Centre shaft concrete work completed upto raft and further work in progress. Partition wall concrete work completed upto column's 3rd lift and gravel soil filling work in progress. Side Walls concrete work completed upto 3rd lift and further work in progress. iv) Flash mixer Designs and drawings approved by SE (PH) (ATP). work not started... v) Chlorination Room Designs and drawings approved by SE (PH) (ATP). work not started... vi) Aerator Designs and drawings approved by SE (PH) (ATP). work not started... 3) HDPE Gravity Main from Housing Board ELSR to Existing Indiramma Colony ELSRs Scope - 2.930 mtrs. Procurement - 2.930 Km. HDPE - 200 mm dia – 2.250 km, Laying - 2.250 km, Tested - 2.250 km. HDPE - 160 mm dia – 0.680 km, Laying - 0.680 km, Tested – 0.680 km. 4) Distribution network: Scope = 41.617 Km, Procurement - 41.617 Km. HDPE - 110 mm dia – 34.665 km, Laying - 34.665 km, Tested – 0.000 km under progress. HDPE - 160 mm dia – 0.135 km, Laying - 0.135 km, Tested – 0.000 km under progress. HDPE - 200 mm dia – 6.817 km, Laying - 6.617 km, Tested – 0.000 km under progress. 5) Pumping main DI K9 - Scope - 125 mtrs Procure -125 mtrs. QAP is approved and awaiting for inspection date. DI K9 - 1200 mm dia – 0.125 km, Laying - 0.000 km, Tested – 0.000 km. Status: - Instructed SE (PH) ATP, to change deliverable MS Pipe instead of DI K9 (125 RMT) Raw Water Pumping Main. 6) DI K7 Distribution Pipelines - Scope -128 mtrs Procure - 128 mtrs, QAP is approved and awaiting for inspection date. DI K7 - 350 mm dia – 0.085 km, Laying - 0.000 km, Tested – 0.000 km. DI K7 - 300 mm dia – 0.043km, Laying - 0.000 km, Tested – 0.000 km. 7) ELSRs- NA 8) HSCs Scope - 5725 No, Procurement - 5725 Nos Given - 3660 No's 9) Raw Water Centrifugal Pump sets in Hundri Neeva Canal (HNSS) - 3 Nos.x112 KW: Yet to procure. 10) Electro Magnetic Flow Meters - 20 Nos - Yet to procure. 11) DI valves Procurement - 67 No's Installing - under progress. 11) Domestic Water Meters with Precast chambers for Existing House Service Connections Scope - 21973 Nos - Procure is pending. Status: Hon’ble MLA requested change the deliverables. SE (PH) ATP inspected the site and instructed to prepare work slip. Work slip is under progress. 12) Payment released till date to contractor – 6.22 in crores. Total Value of work done: Rs.7.50Cr. Balance GoI & GoAP Share: Rs.0.84Cr. Letter sent to APUFIDC for release. 13) Issues: No Land issue. 1. The Contractor was properly and regularly not maintained quality Records and Registers, Documents, Safety Equipment’s at site. 2. Contractor delaying work progress not mobilized for skilled workers for bar benders and shuttering workers. 3. Contract agency not maintained pour card register and steel bar bending schedules. 4. Hydrostatic test is not conducting regularly. 5. Quality Control LAB not installation at site as per Agreement conditions. 6. Work progress very slow.

Project In-Charge Official Details

Name: Mr.N.Eswaraiah
Designation: Municipal Engineer
Email: guntakalmunicipality@gmail.com
Phone: +919849907414

Project Components

News & Updates
  • 7th SHPSC Minutes of Meeting held on 10.05.2017

    Download

  • 6th State Level Technical Committee (SLTC) Minutes of Meeting held on 08.05.2017

    Download

  • 6th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 23.03.2017 under AMRUT

    Download

  • 3rd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 06.01.2017 under AMRUT

    Download

  • 2nd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) under AMRUT

    Download

  • Minutes of 12th Meeting of Apex Committee under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) regarding.

    Download

  • SAAP 2016-17 Documents

    State Annual Action Plan (SAAP) (FY 2016-17) Andhra PradeshDownload