Government of Andhra Pradesh Government of
Andhra Pradesh, India
Andhra Pradesh Urban Finance and Infrastructure Development Corporation (APUFIDC) Andhra Pradesh Urban Finance and
Infrastructure Development Corporation
Municipal Administration & Urban Development (MA & UD)

SAAP 2016-20 Guntakul

Name of the Project
Providing pumping main from WTP to ELSR’s in the town including construction of pump house and supply of pump sets and construction of 2 No’s ELSR’s
Name of the Agency
M/s. KLSR Infrastructure Pvt. Limited.
SAAP Approval Meeting No. & Date by SHPSC SAAP Approved Cost
(In Cr.)
Technical Approval Date of DPR by SLTC Administrative Approval of DPR by SHPSC NIT Approved Administrative Sanction Cost (In Cr.)
6
15/03/2017
8.38 23/03/2017 01/05/2017 09/10/2017
Tender Floated On Last Date of receipt of Tender Tender Type IBM / ECV Value % of Tender
Yes 20/10/2017 Non-EPC
Contract Awarded Cost
(In Cr.)
Contract Awarded On Contract Period (Months) Completion Date Remarks
Guntakal Public Health. ULB: Guntakal Municipality. SAAP - 2016-20 WS (AMRUT PHASE - II) Project cost - 10.98 Crores (Estimate cost) Agency - KLSR infratech Pvt limited. Letter of acceptance Date: 16-02-2018. Contract agreement Date: 05-05-2018, Target date of completion: 05-05-2019, (12 Months) Components - 1) Construction of 7.4 X 6.9 m Pump House at Filtration Plant. Status: Drawings and designs is approved. 2) Pump Sets - 3 no X 49 KW. Status: designs are submitted for approval. 3) DI K9 100 mm to 400 mm dia Transmission Line - 9.06 KM. Status: - Transmission pumping main Pipe Line excavation stated Date: 29.10.2018. As per Agreement – 9.060 km. DI K9 - 400 mm dia - 1.640 km. DI K9 - 350 mm dia - 2.481 km. DI K9 - 250 mm dia – 0.050 km. DI K9 - 200 mm dia – 2.947 km. DI K9 - 150 mm dia – 1.040 km. DI K9 - 100 mm dia – 0.902 km. Procurement - 9.176 Km. DI K9 - 400 mm dia - 1.620 km, Laying - 1.405 km, Tested – 0.000 km. DI K9 - 350 mm dia - 2.478 km, Laying - 0.935 km, Tested – 0.000 km. DI K9 - 250 mm dia – 0.000 km, Laying - 0.000 km, Tested – 0.000 km. DI K9 - 200 mm dia – 3.007 km, Laying - 1.400 km, Tested – 0.000 km. DI K9 - 150 mm dia – 1.644.5 km, Laying - 0.100 km, Tested – 0.000 km. DI K9 - 100 mm dia – 0.423.5 km, Laying - 0.000 km, Tested – 0.000 km. Status: LS is approved. Total Pipe Line Laying: 3.840 Km. Total Pipe Line Testing: 0.000 Km. 4) ELSR s - 02 no's I) Boy's High School ELSR: Boy's High School ELSR designs and drawings approved and approved by SE (PH) ATP. Status: Staircase Concrete work completed upto 1st bracing beam. ELSR - Concrete work completed upto Columns 1st lift (above 1st brace beam) and work was stopped due to Contractor not mobilized for skilled workers for bar benders and shuttering workers. DT:16-11-2018. . II) Gowtham Nagar ELSR designs and drawings approved and approved by SE (PH) ATP. Soils Sample collected DT: 08-07-2018. Status: Staircase - Concrete work completed upto column’s 1st lift above the bracing beam and first flight reinforcement work is in progress. ELSR - Concrete work completed upto column’s 2nd lift above the 3rd brace beam and further work in progress. 5) Payment released till date to contractor – Nil. Total Value of work done: Rs.4.500Cr. Bill submitted: 2.81 Cr. Contractor Amount Paid: Rs. Nil Cr. ISSUES: 1. The Contractor was properly and regularly not maintained Safety Equipment’s at site. 2. Contractor delaying work progress not mobilized for skilled workers for bar benders and shuttering workers. 3. Contract agency Sand bed and encasing provided only chemically reactive soils and in hard rock areas. 4) Permission from R&B dept. is required to lay pipe line along Kasapuram road is required. 5) R&B road crossing permission is required at Aluru road & Kasapuram road 6) Two - Railway crossing permission got and agreement is completed. One - Railway area pipe line permission got and another railway area permission got unofficially at railway dept. Officially this two permission is pending at railway department. 7) Notice letter issued form PH DEE to KLSR infra regarding not grounding the work, DT: 26-06-2018. 8) 3rd Notice letter issued form PH AE madam to KLSR infra regarding Not deputed Technical staff DT: 19-09- 2018. 7) Requested Letter issued form PH DEE to Guntakal Commissioner Laying of pumping main along the alignment – site clearance DT: 07-12-2018. 9) Letter issued form PH AE ma’am to KLSR infra regarding Certain remarks in work execution DT: 08-12- 2018. Technical staff DT: 19-09- 2018.

Project In-Charge Official Details

Name: Mr.C.H.Prasad
Designation: Executive Engineer
Email: eephatp@yahoo.co.in
Phone: +918639066768

Project Components

News & Updates
  • 7th SHPSC Minutes of Meeting held on 10.05.2017

    Download

  • 6th State Level Technical Committee (SLTC) Minutes of Meeting held on 08.05.2017

    Download

  • 6th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 23.03.2017 under AMRUT

    Download

  • 3rd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 06.01.2017 under AMRUT

    Download

  • 2nd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) under AMRUT

    Download

  • Minutes of 12th Meeting of Apex Committee under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) regarding.

    Download

  • SAAP 2016-17 Documents

    State Annual Action Plan (SAAP) (FY 2016-17) Andhra PradeshDownload