Government of Andhra Pradesh Government of
Andhra Pradesh, India
Andhra Pradesh Urban Finance and Infrastructure Development Corporation (APUFIDC) Andhra Pradesh Urban Finance and
Infrastructure Development Corporation
Municipal Administration & Urban Development (MA & UD)

SAAP 2016-20 Guntakul

Name of the Project
Providing pumping main from WTP to ELSR’s in the town including construction of pump house and supply of pump sets and construction of 2 No’s ELSR’s
Name of the Agency
M/s. KLSR Infrastructure Pvt. Limited.
SAAP Approval Meeting No. & Date by SHPSC SAAP Approved Cost
(In Cr.)
Technical Approval Date of DPR by SLTC Administrative Approval of DPR by SHPSC NIT Approved Administrative Sanction Cost (In Cr.)
6
15/03/2017
8.38 23/03/2017 01/05/2017 09/10/2017
Tender Floated On Last Date of receipt of Tender Tender Type IBM / ECV Value % of Tender
Yes 20/10/2017 Non-EPC 4.490
Contract Awarded Cost
(In Cr.)
Contract Awarded On Contract Period (Months) Completion Date Remarks
10.09 16/02/2018 12 15/02/2019 Work Status: Letter of acceptance Date: 16-02-2018. Contract agreement Date: 05-05-2018, Target date of completion: 05-05-2019, (12 Months) EOT Submitted Date: 14-05-2019. (Waiting for Approval) Components - 1) Construction of 7.4 X 6.9 m Pump House at Filtration Plant. Concrete work completed upto slab bottom and further work in progress. 2) Pump Sets - 3 no X 49 KW. Status: designs approved by the SE (PH) ATP office. DT: 06-02-2019. 3) DI K9 100 mm to 400 mm dia Transmission Line - 9.06 KM. Transmission pumping main Pipe Line excavation stated Date: 29.10.2018. As per Agreement – 9.060 km. DI K9 - 400 mm dia - 1.640 km. DI K9 - 350 mm dia - 2.481 km. DI K9 - 250 mm dia – 0.050 km. DI K9 - 200 mm dia – 2.947 km. DI K9 - 150 mm dia – 1.040 km. DI K9 - 100 mm dia – 0.902 km. Procurement - 9.176 Km. DI K9 - 400 mm dia - 1.620 km, Laying - 1.284 km, Tested – 0.000 km. DI K9 - 350 mm dia - 2.478 km, Laying - 2.058 km, Tested – 0.000 km. DI K9 - 250 mm dia – 0.000 km, Laying - 0.000 km, Tested – 0.000 km. DI K9 - 200 mm dia – 3.007 km, Laying - 2.491 km, Tested – 0.000 km. DI K9 - 150 mm dia – 1.644.5 km, Laying - 1.012 km, Tested – 0.000 km. DI K9 - 100 mm dia – 0.423.5 km, Laying - 0.374 km, Tested – 0.000 km. Status: LS is approved. Total Pipe Line Laying: 7.219 Km. Total Pipe Line Testing: 0.000 Km. 4) ELSR s - 02 no's I) Boy's High School ELSR: Staircase - Concrete work completed upto 1st bracing beam. ELSR - Concrete work completed upto Columns 1st lift above 1st brace beam and work was stopped due to Contractor not mobilized for skilled workers for bar benders and shuttering workers. DT:16-11-2018. II) Gowtham Nagar ELSR Staircase - Concrete work completed up to 7th flight. ELSR - Concrete work completed up to dome ring beam bottom. 5. Payment: 1. Value of work done (in cr) - 4.8 Cr's. 2. Value of bills submitted (in cr) - 3.36 Cr's. 3. Mobilization advance paid (if any) (in cr) - Nil 4. Value of bills paid (in cr) - 0.74 Cr's. 5. Cfms number for pending payment. i. CMFS Bill No.2019-317337 Amount Rs.0.42 Cr's (PAO Anantapur) ii. CMFS Bill No. is not generate, Amount Rs. 0.33 Cr's ISSUES: 1. The Contractor was properly not maintained Safety precautions, they not doing proper backfilling like compaction and levelling at site. 2. Contractor delaying work progress not mobilized for skilled workers for bar benders and shuttering workers. 3. Contract agency Sand bed and encasing provided only chemically reactive soils and in hard rock areas, Hydrostatic test is not conducting the contract agency and Road restoration work not doing the contract agency.. 4) R&B Road Permissions i). Permission given by R&B department along Kasapuram road laying of pipe line At Km CH: 0/060 to 0/210, Km CH: 0/313 to 2/008 Total berm cutting for a Length of the road - 1845.00 mts. road cutting restoration charges pending at PH Department. Letter NO: 623/Road Cutting /TA/2018-19, Date: 29-11-2018. ii). Kasapuram Road pipe line crossing Permission given by R&B department , the BT road at Km CH: 1/318 for a length of 15.00 Mts, road cutting restoration charges pending at PH Department. Letter NO: 623/Road Cutting /TA/2018-19, Date: 29-11-2018. Letter NO: 623/Road Cutting /TA/2018-19, Date: 29-11-2018. iii). Alur Road pipe line crossing permission given by R&B department, at Km CH: 1/8 for a length of 7.70 Mts road cutting restoration charges pending at PH Department. Letter NO: 624/Road Cutting /TA/2018-19, Date: 29-11-2018. 5) One - Railway area pipe line permission got and another railway area permission got unofficially from railway dept. officially this two permission is pending at railway department. Railway Authorities not permit the laying of 200mm dia DI pipe on existing ROBs near Railway station - letter - 12.02.2019 6). Work stopped due to Shortage of funds.

Project In-Charge Official Details

Name: Mr.C.H.Prasad
Designation: Executive Engineer
Email: eephatp@yahoo.co.in
Phone: +918639066768

Project Components

News & Updates
  • 7th SHPSC Minutes of Meeting held on 10.05.2017

    Download

  • 6th State Level Technical Committee (SLTC) Minutes of Meeting held on 08.05.2017

    Download

  • 6th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th SHPSC Minutes of Meeting (MoM) under AMRUT

    Download

  • 5th State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 23.03.2017 under AMRUT

    Download

  • 3rd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) held on 06.01.2017 under AMRUT

    Download

  • 2nd State Level Technical Committee (SLTC) Minutes of Meeting (MoM) under AMRUT

    Download

  • Minutes of 12th Meeting of Apex Committee under the Atal Mission for Rejuvenation and Urban Transformation (AMRUT) regarding.

    Download

  • SAAP 2016-17 Documents

    State Annual Action Plan (SAAP) (FY 2016-17) Andhra PradeshDownload