SAAP 2015-16 PROJECTS AT A GLANCE (TENDER STATUS)

S.No.SectorProject Cost
(In Cr.)
Total ProjectsTenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedAwarded Cost
(In Cr.)
Awarded %
(Cost)
Awarded %
(Numbers)
1Water Supply797.93262423237151723585.1373.3388.46
StatusRemarks / Comments
DPR Design Stage (2): Vijayawada,Nellore
Tender Stage (1): Chittoor



2Parks & Green Spaces16.073434343231003010.7466.8388.24
StatusRemarks / Comments
Tender Stage (2): Kakinada,Tirupathi
COT Approved (1): Guntakul



Total814.006058575538151753595.8773.2088.33

SAAP 2016-20 PROJECTS AT A GLANCE

S.No.SectorNo. of ProjectsSAAP Approved Cost (Cr.)SLTC ApprovedAS AccordedTS AccordedTenders FloatedAwarded
1Water Supply291336.742929272618
2Sewerage & Septage Management26495.442626252522
3Storm Water Drainage7289.7177774
4Parks & Green Spaces3218.29323231310
Total942140.189494908944

SAAP 2016-20 PROJECTS AT A GLANCE (TENDER STATUS)

S.No.SectorProject Cost
(In Cr.)
Total ProjectsTenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedAwarded Cost
(In Cr.)
Awarded %
(Cost)
Awarded %
(Numbers)
1Water Supply1785.502926262331718181154.1964.6462.07
StatusRemarks / Comments
Administrative Sanction (AS) Accorded (29): Srikakulam,Vizianagaram,GVMC,Tadepalligudem,Bhimavaram,ELURU,Machilipatnam,Gudivada,Guntur,Narasaraopeta,
Chilakaluripeta,Ongole,Nellore,Nellore,Tirupathi,Chittoor,Madanapalli,Dharamavaram,Guntakul,Kadapa,
Kurnool,Adoni,Nandyala,Ananthapuramu,Hindupur,Tadipatri,Proddutur,Kavali,Srikalhasthi
Technical Sanction(TS) Accorded (27): Srikakulam,Vizianagaram,GVMC,Tadepalligudem,Bhimavaram,ELURU,Machilipatnam,Gudivada,Guntur,Narasaraopeta,
Chilakaluripeta,Ongole,Tirupathi,Chittoor,Madanapalli,Dharamavaram,Guntakul,Kadapa,Kurnool,Adoni,
Nandyala,Ananthapuramu,Hindupur,Tadipatri,Proddutur,Kavali,Srikalhasthi
Tender Stage (3): Guntur,Chittoor,Srikalhasthi
Awarded (21): Vizianagaram,GVMC,Tadepalligudem,Bhimavaram,ELURU,Machilipatnam,Gudivada,Narasaraopeta,Chilakaluripeta,Ongole,
Tirupathi,Madanapalli,Dharamavaram,Kadapa,Adoni,Nandyala,Ananthapuramu,Hindupur,Tadipatri,Proddutur,
Kavali



2Sewerage & Septage Management825.73262521160162218466.1956.4669.23
StatusRemarks / Comments
Administrative Sanction (AS) Accorded (26): Srikakulam,Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,
Gudivada,Tenali,Chilakaluripeta,Ongole,Tirupathi,Chittoor,Madanapalli,Dharamavaram,Guntakul,Kadapa,
Kurnool,Adoni,Nandyala,Ananthapuramu,Kavali,Srikalhasthi
Technical Sanction(TS) Accorded (25): Srikakulam,Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,
Gudivada,Tenali,Chilakaluripeta,Ongole,Tirupathi,Madanapalli,Dharamavaram,Guntakul,Kadapa,Kurnool,
Adoni,Nandyala,Ananthapuramu,Kavali,Srikalhasthi
Tender Stage (6): Vizianagaram,Rajahmundry,Machilipatnam,Tenali,Chilakaluripeta,Kadapa
Awarded (16): GVMC,Kakinada,Tadepalligudem,Vijayawada,Gudivada,Ongole,Tirupathi,Madanapalli,Dharamavaram,Guntakul,
Kurnool,Adoni,Nandyala,Ananthapuramu,Kavali,Srikalhasthi



3Storm Water Drainage350.7577630244178.8851.0057.14
StatusRemarks / Comments
Administrative Sanction (AS) Accorded (7): Srikakulam,Rajahmundry,Kakinada,Machilipatnam,Nellore,Tirupathi,Ananthapuramu
Technical Sanction(TS) Accorded (7): Srikakulam,Rajahmundry,Kakinada,Machilipatnam,Nellore,Tirupathi,Ananthapuramu
Tender Stage (3): Srikakulam,Rajahmundry,Ananthapuramu
Awarded (3): Kakinada,Nellore,Tirupathi



4Parks & Green Spaces36.613231292625002317.2547.1271.88
StatusRemarks / Comments
Administrative Sanction (AS) Accorded (32): Srikakulam,Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,
Gudivada,Tenali,Guntur,Narasaraopeta,Chilakaluripeta,Ongole,Nellore,Tirupathi,Chittoor,Madanapalli,
Dharamavaram,Guntakul,Kadapa,Kurnool,Adoni,Nandyala,Ananthapuramu,Hindupur,Tadipatri,Proddutur,
Kavali,Srikalhasthi
Technical Sanction(TS) Accorded (31): Srikakulam,Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,
Gudivada,Tenali,Guntur,Narasaraopeta,Chilakaluripeta,Ongole,Nellore,Tirupathi,Chittoor,Madanapalli,
Dharamavaram,Guntakul,Kadapa,Kurnool,Adoni,Nandyala,Ananthapuramu,Hindupur,Proddutur,Kavali,
Srikalhasthi
Tender Stage (3): Vijayawada,Madanapalli,Dharamavaram
COT Approved (5): Bhimavaram,Machilipatnam,Tenali,Guntur,Hindupur
Awarded (21): Srikakulam,Vizianagaram,Rajahmundry,Kakinada,Tadepalligudem,ELURU,Gudivada,Narasaraopeta,Chilakaluripeta,Ongole,
Nellore,Tirupathi,Chittoor,Guntakul,Kadapa,Kurnool,Adoni,Nandyala,Proddutur,Kavali,
Srikalhasthi



Total2998.5994898268283544631816.5160.5867.02

SAAP 2015-16 Projects

1. Status of Water Supply Projects (2015-16)

S.No.ULB NameProject Cost
(In Cr.)
Tenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedRemarks
1Srikakulam10.7320.08.2016
Yes
YesYesYes30.12.2016
Yes
1. Number of HSC given "2885" (out of 10000).
2. Procurement of Pipe "38" km (out of 38 km).
3. Distribution network laid "37.5" km (out of 38 km).
2Vizianagaram5.8526.09.2016
Yes
YesYesYes24.04.2017
Yes
WORK STARTED FROM 12/07/2017.As on date .810 HSC connection are given out of 7417.
3GVMC153.1805.09.2017
Yes
YesYesYesYes14.11.2017
Yes
Designs and drawings approval awaited for zone 3 , WS HSC Surveying in progress. Procured
Quantity HDPE DN200 - 30.00kms, DN160- 70.00kms, DN 250- 10.0kms, DI K7 400mm - 1200mts. HDPE
Components :
1.HSC - 78,024 Nos.
2.D'system - HDPE PN6, PE100 DN 160mm is 55096 / 159299 mts, 200mm is 20778 / 98590 mts, 250mm is 8592 / 51020 mts.
DI K7 Gravity main - 300mm - 121 / 2600mts, 400mm - 0 / 1200mts, 500mm - 0 / 1000mts, 600mm - 0 / 2100mts.
4Rajahmundry2.8307.10.2016
Yes
YesYesYesNo01.03.2017
Yes
No of HSC Completed"698'' Nos (out of 2900).
5Kakinada41.4429.09.2016
Yes
YesYesYesYes22.05.2017
Yes
1.Number of HSCs given "3345" (out of 20415).
2. Procurement of Pipe "113.677" km (out of 113.677 km).
3. Distribution network laid "78.800" km (out of 113.677 km).
6Tadepalligudem15.4027.09.2016
Yes
YesYesYesYes02.03.2017
Yes
1.HSC(HDPE/PVC Pipes)- 4522Nos,95 Nos given
2.Distribution Network(DI K7 & HDPE Pipe)-51.455Km. 18.574Km Procured,3.500Km Laid, 0.000Km Tested
3.SUMP(600KL)-Shuttering work is in progress for cylindrical side wall 2nd lift
4.Pump house(13.00X6.00Mts)-1Nos-Works to be started.
5.ELSR(1000KL)-1Nos- i)3rd Level Brace beam steel placement work is in progress
6.Pumping mains(DI K9 Pipe)-3.860Km, 3.855.5Km Procured, 1.888Km Laid, 0.000Km Tested
7Bhimavaram47.2928.09.2016
Yes
YesYesYesYes27.05.2017
Yes
1. Number of HSCs given a"0" (out of 20668).
2. Procurement of Pipe "60." km (out of 126 km).
3. Distribution network laid "51.250" km (out of 126 km).
4. Procurement of Pipe "4.6" km (out of 5.5 km).
5. Transmission network laid "2.6" kms (out of 5.5 km).
8ELURU2.9607.11.2016
Yes
YesYesYesYes14.02.2017
Yes
HSC Executed as on date :19.07.2018- (705/6482 )
{{(Note:-
1).Execution of tap connections is in slow progress due to non availability of a[[lications from House holds.
Some of the reson are:-
2).In ERP module the property tax assessment number is mandatory for entering the tap applications.
3). Some of the houses (without tap connections) are not having property tax assessments for which they have no ownership rights.
4). Some of the houses which are having property tax assessment in the name of their elders who are not alive and transfer of title is not done due to various reasons.
5). Some of the house owners not having BPL cards in their name for which they are not eligible for BPL tap connections and they are not able to pay General category donation charges.)}}
( Executed for the Month of November-2017-HSCs-52nos only )
( Executed for the Month of December-2017-HSCs-79nos only )
( Executed for the Month of January-2018-HSCs-33nos only )
( Executed for the Month of Feb-2018-HSCs-22nos only )
( Executed for the Month of March--2018-HSCs-57nos only ) ( Executed for the Month of APRIL--2018-HSCs-49nos only )
9Vijayawada87.43NoNoNoNoDPR under Scrutiny.
10Machilipatnam36.7530.09.2016
Yes
YesYesYes10.03.2017
Yes
1. Material procurement completed. Number of HSC given "0" (out of 9095)
2.Pumping main work progress was DI Pipes 8.254Km procured(Out of 8.4 Km.)
250mm DI K9 Pumping main, 605mts laid out of 1680mts.
200mm DI K9 Pumping main, 330mts laid out of 1790mts.
150mm DI K9 Pumping main, 33mts laid.
3.Distribution lines work progress is " 0 " (Out of 186.4 Km.)
4
1. Second Brace Beam centering work is in progress at Valandapalem ELSR (700 KL)site .{(Out of 4 ELSR s ) 2 are 700 KL and 2 are 500 KL capacity}
2. Second Brace Beam centering work is in progress at Rustumbada ELSR (700 KL)
11Gudivada32.4726.09.2016
Yes
YesYesYesYes02.03.2017
Yes
Physical Progress = 19%
1. 500 KL ELSR: Third tier 12 nos. Braces / Chords casting completed.
2. 900 KL ELSR: 24 nos 1st lift Columns casting completed. 1st Tier Braces / Chords (24 Nos.) & Tie Beams (12 Nos.) Steel Reinft. Placing under progress
3. Procurement of pumping mains completed. Delivery at site in progress. Received 6.50 Km out of 7.14 Km
4. Factory Inspection / Tests for Distribution Lines (HDPE pipes) completed. Procurement in progress.
12Tenali8.5927.12.2016
Yes
YesYesYes17.05.2017
Yes
1. Number of HSC's given and Geo-tagged "5952” (out of 21748).
13Guntur22.0226.09.2016
Yes
YesYesYesYes01.02.2017
Yes
1. Number of
HSCs given and Geo-tagged "1831"
(out of 56902).
2. Procurement of Materials completed for 13000 nos HSC(out of 56902)
3.Survey work is in progress.
14Narasaraopeta13.0322.09.2016
Yes
YesYesYesYes12.06.2017
Yes
1. 800 KL ELSR bottom dome Side wall 1st lift concrete work Completed and stair case Columns between 10th& 11th flight concrete work completed.
2. House service connection Work started and 610 no's f connection were given out 1400 no's.
3. Distribution system of hdpe pipes laying completed up to 7.2 km out of 20km.
4. 8 mts dia sump cum pump house 1st lift column concrete completed above floor slab ,curing work is in progress .
5. DI K7 600 mm dia of length 1.5 km :Pipeline laying work started and completed up to 1485 mts and inter connections work is in progress.


15Chilakaluripeta8.8217.08.2016
Yes
YesYesYes27.02.2017
Yes
1) 15.0 KM HDPE Pipes procured.
2)HSC'S material procured.340 No's house connections given,work in progress.
3)pumphouse/Sump of Dia 4mts Completed.
4) Distribution network pipe laying work of 11km/15KM completed.Work in progress.
5) M/s Velko Infrastructure received a part Bill(material procurement bill) of Amount Rs.1,05,00,000/-
6) For 1300 KL ELSR,bottom dome steel reinforcement placing in progress.Stair case upto dome level completed.
7) M/s velko infrastructure ltd has taken a part bill of Amount Rs 2,50,00,000/-
16Ongole2.8818.08.2016
Yes
YesYesYes23.06.2017
Yes
1.contractor agreement concluded.
2. Factory inspection for HSC material on 21.12.2017.
3. HSC works to be started immediately.
4.work still not started,informed to m.e sir.contractor responding but not starting the work.
Today also informed contractor to start work immediately.4.Ulb informed contractor to start work immediately, again he is saying with in two days we will start work..
5.Continuously following up contractor by ulb and still work is not started.
8.works to be started shortly.
9.collecting of applications from beneficiaries of different areas started.
Work to be started shortly.8.Identified beneficiaries and work will start shortly.
8.Today list of beneficiaries has collected by contractor and preparing to start HSC from Tomorrow onwards.
11.At last HSC work has been started by contractor,and planning to give 10 connections today.
11.Hscwork started and til now 40 connections has given by contractor.
17Nellore10.00NoNoNoNoThis project is proposed to be dropped as the comprehensive water supply scheme is taken up under HUDCO scheme. Hence the funds of this project is proposed to be utilized for the SAAP 2016-20 project.
18Tirupathi93.7123.08.2016
Yes
YesYesYesYes13.02.2017
Yes
1) Pumping/Gravity Main-
I. 400mm DI K7 pipe – Scope 1210 m Supply 1210 m and laying 1165 m, Hydro testing – 0 m
II. 500mm DI K7 pipe – Scope 2490 m Supply 2490 m and laying 2119.5 m, Hydro testing – 800 m
III. 600 mm dia K9 pipes – Scope 100 Supply 100 m Laying 0 m, Hydro testing – 0 m
IV. 600 mm dia K7 pipes – Scope 9960 m Supply 9958.5 m and Laying 6857 m, Hydro testing – 1800 m
2) ELBR-
I. WTP Mangalam ELBR (500 KL) – Slip form is in progress
3) Feeder Main-
I. 200mm DI K7 pipe – Scope 2060 m Supply 2057 m and laying 1178.5 m, Hydro testing – 0 m
II. 250mm DI K7 pipe – Scope 500 m Supply 472.5 m and laying 397.5 m, Hydro testing – 0 m
III. 350 mm DI K9 pipe- Scope 1540 m Supply 1539 m and laying 358.00 m, Hydro testing – 0 m
IV. 400mm DI K9 pipe – Scope 1390 m Supply 138 m and laying 0 m, Hydro testing – 0 m
4) ELSR 11 no’s-
I. Mahila University ELSR (1500 KL) - Concrete work for columns completed up to 7.56 m
II. Padmavathi Park ELSR (1500 KL) - Concrete work for top doom slab completed
III. Auto Nagar-2 ELSR (600 KL) near UDS office - Concrete work for top doom slab completed
IV. Rajeev Nagar ELSR (1350 KL) – Shuttering work for top doom slab is in progress
V. Lakshmi Puram-2 (1000 KL)- Bottom dome slab shuttering work is in progress
VI. Auto Nagar-1 ELSR (1000 KL) – Bottom dome slab shuttering work is in progress
VII. Prakasham Park ELSR (1700 KL) - Concrete work for top doom slab completed
VIII. Bhupal Housing Colony ELSR (1000 KL) - Concrete work for top doom slab completed
IX. Lakshmi Puram-1(1000 KL) - Concrete work for columns completed up to 6.955 m
X. NGO colony ELSR (1800 KL) – Concrete work for Bottom dome slab completed
XI. SPJNM School ELSR (1150 KL) - Concrete work for top doom slab completed
XII. Railway colony ELSR (2000 KL)-PCC completed below ground level
5) Distribution network-
I. 110 mm dia HDPE pipe – Scope 105523 m Supply 60600 m and laying 58607 m, Hydro testing – 0 m
II. 160 mm dia HDPE pipe - Scope 19267 m Supply 14570 m and laying 9991 m, Hydro testing – 0 m
III. 200 mm dia HDPE pipe - Scope 2000 m Supply 2000 m and laying 1714 m, Hydro testing – 890 m
IV. 250 mm dia HDPE pipe - Scope 10215 m Supply 5467 m and laying 2816 m, Hydro testing – 0 m
V. 315 mm dia HDPE pipe - Scope 648 m Supply 648 m and laying 600 m, Hydro testing – 580 m
6) House Service Connections
I. HSC –Scope 19464 No’s-Procured 9962 No’s -HSC completed -6295 No’s (Replaced)
II. HSC –Scope 5862 No’s-Procured 2931 No’s -HSC completed -24 No’s (New Connections)
7) Payment- Work done till date by the contractor Rs.51 Cr-Released till date to the contractor-Rs.26.20 Cr
8) Issues-
I. Contractor not maintaining registers like site order book, concreting register and stock registers of materials etc.
II. Mobilization of more man power is needed for pipe laying and HSC works
19Chittoor2.8827.03.2017
Yes
NoNoNoIt is proposed in 8th SLTC to delete this project and transfer the funds to Chittoor WS project under SAAP 2016-20.
20Madanapalli19.0004.08.2016
Yes
YesYesYesYes03.02.2017
Yes
Physical Progress Achieved - 1.38 %
1) A. V. Naidu Colony ELSR (1000 KL) –Tank bottom slab reinforcement work in progress.
2) NVR layout ELSR (700 KL) - Area under hold due to Walkers Association.
3) Dhobi ghat ELSR (1250 KL) - Site to be Relocated New proposed land belongs to Revenue Department Alienation process initiated by ULB.
4) HDPE pipes procured 10 km. Laying started on 22.12.2017. Works to be expedited.
5) HDPE 110mm Dia Pipe Laying 3.855 KM was layed, and 160mm dia 0.202 mts was layed, and 200mm dia 0.148 mts was layed.
5) HSC QAP Approved .HSC 7800 Nos Procured works to be expedited.
21Dharamavaram17.5722.09.2016
Yes
YesYesYesYes15.06.2017
Yes
1) HSC's (Nos) - Scope - 8287, Material procured. work yet to start.
2) Distribution Network - Scope -
a. Scope - 41502 m HDPE -1.33 km laying completed .
b. Scope - 2280 DI K7 - QAP submitted and approved. Factory inspection completed. Material reached at site. Laying yet to start.
3) 350 KL Sump Well @ Erragunta PH - Works yet to start.
4) Construction of pump house - 1 no.- work yet to start.
5) ELSRs (3 Nos)
a) 750 KL @ Siddaiahgutta - Siddhaiah Gutta Site Boulders, clearance progress.
b) 800 KL @ Lakshmi Nagar - Land has been surveyed and boundaries have been marked, A legal notice has been issued for local residents.
c) 850 KL @ Indiramma Colony - Bar bending in progress at ground level radial beam in progress.
6) Transmission Mains - Scope - 4476 m, -1.54 km laying completed.
7) Centrifugal pump sets at kethi reddy HWW and Erraguntla HWW -12 no.s - yet to procure.
22Guntakul16.4504.10.2016
Yes
YesYesYesYes11.08.2017
Yes
1) Survey work starting date: 19.09.2017.
2) Revised designs of 5 MLD WTP to be submitted by contractor.
3) Soil samples from the WTP AND OFTAKE WELL cum PUMP HOUSE sites have been collected and testing
completed. Designs to be submitted by contractor.
4) 5 MLD Filtration plant flow diagram approved and Detailed Designs under scrutiny.
5) Distribution HDPE Pipes Scrutinized and approved by SE (PH) ,ATP and Total Pipes are procured by Contractor. Work
is under progress.
6) Quality of HDPE Pipes testing and Inspection is completed by the Third Party Inspection Agency on Dt:16-12-2017
at Vijaya Polymers India Pvt ltd. and materials are procured by contractor.
7) Detailed Designes submitted to SE (PH) ATP, for 8m Dia off Take well cum pump house at HNSS Canal. Designs
under Scrutiny.
8) For House Service Connections testing and Inspection is completed by Third Party Inspection Agency on Dt:26-12-
2017 at kimplas Piping System, Nashik and Materials are procured by Contractor.
9) MDPE pipes testing and inspection completed by Third Party Inspection Agency on Dt:30-12-2017 at Dura Line India
Pvt Ltd, Hyderabad and Materials are procured by Contractor.
10) Distribution pipe line designs and drawings approved, Distribution pipe line excavation is stared.
11) Deposit of cost of land acquisition requested letter issued from RDO office to GMC Commissioner. Dt: 24-01-2018.
13) 5 MLD Filtration plant flow diagram and Detailed Structural Designs, Drawings approved by SE (PH) Dt:
07/02/2018.
14) Indiramma colony - I, Proterline to Bharmashala and Prashanthi nagar colony distribution and distribution main line
earth work excavation and laying is completed.
15) HSC work starting date: 12.02.2018.
16) Offtake well cum Pump house in Hundri Neeva Canal (HNSS) at Guntakal - 8.0m trs dia
Staus : Leveling work completed.Levels changes in Offtake well cum Pump house and Detailed Structural Designs,
Drawings are Re-submiited for Design Approval to SE PH(ATP).
17) WTP - 5.00MLD Capacity Rapid Gravity Filtration Plant.
Staus : Leveling work completed. Levels changes in 5 MLD Filtration plant flow diagram and Detailed Structural
Designs, Drawings are Re-submiited for Design Approval to SE PH(ATP).

18) HDPE Gravity Main from Housing Board ELSR to Existing Indiramma Colony ELSRs Scope - 2.930 mtrs.
2.930 Km procurement
2.900 km laid
0.000 km tested

19) Pumping main DI K9 - Scope - 125 mtrs
Procure -125 mtrs
Laying - 0 Km
Test- 0 Km
20) ELSRs- NA
21) Distribution network: Scope = 41.617 Km,
procurement - 41.617 Km.
Laying - 36.000 km.
Testing - 0.000 km.
DI K7 Distribution Pipelines - Scope -128 mtrs
Procure - 128 mtrs
Laying – 0 Km
Testing – 0 km.

22) HSCs Scope - 5725 No,
Procurement - 5725 Nos
Given - 250 Nos

23) Raw Water Centrifugal Pump sets in
Hundri Neeva Canal (HNSS) - 3 Nos.x112 KW :Yet to procure.

24) Electro Magnetic Flow Meters - 20 Nos - Yet to procure.

25) Domestic Water Meters with Precast chambers for Existing House Service Connections Scope - 21973 Nos -
Procure is pending.

26) Payment released till date to contractor - 2,60,00,000/- in crores.
19) Some changes in Offtake well cum Pump house and 5 MLD Filtration plant flow diagram and Detailed Structural Designs, Drawings are Re-submiited for Design Approval to SE PH(ATP).
23Kadapa43.3208.09.2017
Yes
YesYesYesYes19.01.2018
Yes
DI Pipes, HDPE Pipes & Air valves, Gate valves was supplied to site
Rs.9.24 Cr Work slip was submitted to government and awaited from committee III
From Gandhi Head water works to DI K9 200mm Dia pipe laying work is in progress at patha kadapa
24Kurnool68.2530.07.2016
Yes
YesYesYesYes06.02.2017
Yes
Physical Progress achieved – 40 %
1) HSC supply 4000 nos. HSC laid –4086nos.
2) HDPE Pipe 110 mm dia Supply - 190 Km, Laying –177.75 KM
3) HDPE Pipe 160 mm dia Supply – 68 Km, Laying – 64.0 KM
4) HDPE Pipe 200 mm dia Supply – 22 Km, Laying – 7.034KM
5) HDPE Pipe 250 mm dia Supply – 3.4 Km, Laying – 1.959 KM.
6) HDPE Pipe 315 mm dia Supply - 0 Km, Laying - 0 Km.
7) HDPE Pipe 355 mm dia Supply - 0 Km, Laid - 0 Km.
8) HDPE Pipe 400 mm dia Supply - 0 Km, Laid - 0 Km
9) Hydrostatic Pressure Test Conducting Started on dt 16/11/2017. Hydrotesting to be expedited.
10) Laying and HSC works to be expedited
11)Agency is working from 24-1-2018
25Adoni12.5401.10.2016
Yes
YesYesYesYes20.09.2017
Yes
1) Preliminary survey started on 10.11.2017 and completed on 23.11.2017.
2) Notice issued by ULB to Contractor for slow progress on 18.12.2017.
3) 2nd notice issued by ULB to contractor to speedy progress of work on 11.01.2018.
4) Designs submitted & taken approval from ULB on 25.01.2018, designs submit to Ph S.E for final Approval.
5) Correction designs submitted & taken approval from ULB on 14.02.2018, designs submit to Ph S.E for final approval.
6) Received QAP of HDPE pipes, fittings, valves & HSC for approval.
7) QAP of HDPE pipes, fittings, valves & HSC got approved waiting for inspection.
8) Joint inspection completed on 08.03.2018 along with ULB ME, DEE's at Maruti tubes pipes factory on 110mm PN6- 17000 mts, 160mm PN6 - 2500 mts, 200mm PN6- 2000 mts & 250mm PN6 - 2000 mts HDPE pipeline & fittings.
9) Joint inspection completed on 14.03.2018 along with ULB ME, DEE for HSC- 1/2''- 1800 Nos at Kimplas factory, Nashik.
10)Joint inspection completed on 15.03.2018 along with ULB ME, DEE for Air valves 80mm - 15Nos & sluice valves 100mm - 68 nos, 150mm - 25 nos, 200mm - 20, 250mm - 16 nos at Mayur valves factory, Nashik.
11)HDPE pipes 110mm PN6- 17000 mts, 160mm PN6 - 2500 mts, 200mm PN6- 2000 mts & 250mm PN6 - 2000 mts, total - 23.5 KMS out of 75.765KM & fittings received to site.
26Nandyala22.5427.08.2016
Yes
YesYesYesYes28.06.2017
Yes
1. HDPE pipe scope 22 Km, procurement 22 Km, laying 11 Km. Work to be expedited.
2. HSC material received at site. HSC works to be started.
3. 1000 KL ELSR at RDO bungalow - up to G+2 bracing completed.
4. 1000 KL ELSR at APHB colony - up to G+2 brace beam bar bending work in progress ,
5. DI pipe line NGO colony water tank to New Elsr Aphb colony water tank gravity line 250 Dia pipe 680 mtrs pipe laid
6.DI pipe line 300 dia 600 mtrs laid.

2. Status of Parks Projects (2015-16)

S.No.ULB NameProject Cost
(In Cr.)
Tenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedRemarks
1Vizianagaram0.5003.11.2016
Yes
YesYesYes21.01.2017
Yes
Work under progress.
2GVMC1.0701.06.2017
Yes
YesYesYes01.07.2017
Yes
Works started
3Rajahmundry0.5007.10.2016
Yes
YesYesYes11.11.2016
Yes
Work under progress.
4Kakinada0.7524.11.2016
Yes
YesNoNoRecalled tenders. Tenders disqualified.
5Tadepalligudem0.3605.12.2016
Yes
YesYesYes11.01.2017
Yes
Work order issued and yet to be started.
6Tadepalligudem0.1405.12.2016
Yes
YesYesYes11.01.2017
Yes
Work order issued and yet to be started.
7Bhimavaram0.5019.11.2016
Yes
YesYesYes08.02.2017
Yes
Civil work is under progress.
8ELURU0.5020.04.2016
Yes
YesYesYes06.05.2016
Yes
Pathway works is under progress and 80% of civil works completed.
9Vijayawada0.2527.06.2016
Yes
YesYesYes23.09.2016
Yes
Work in progress.
10Vijayawada0.2527.06.2016
Yes
YesYesYes18.07.2016
Yes
Work in progress.
11Vijayawada0.2527.06.2016
Yes
YesYesYes18.07.2016
Yes
Work in progress.
12Vijayawada0.2527.06.2016
Yes
YesYesYes18.07.2016
Yes
Work in progress.
13Machilipatnam0.5019.10.2016
Yes
YesYesYes15.02.2017
Yes
Work order issued and work is yet to be started.
14Gudivada0.5025.10.2016
Yes
YesYesYes18.01.2017
Yes
Work order issued and work is yet to be started.
15Tenali0.5007.10.2016
Yes
YesYesYes17.11.2016
Yes
Earth work and compound wall work is under progress.
16Guntur0.5010.06.2016
Yes
YesYesYes18.07.2016
Yes
Gazebo work is in progress (40%)
17Narasaraopeta0.5003.10.2016
Yes
YesYesYes02.12.2016
Yes
Jungle clearance work is under progress (5%)
18Chilakaluripeta0.5023.09.2016
Yes
YesYesYes01.12.2016
Yes
Jungle clearance work is under progress.
19Ongole0.5011.08.2016
Yes
YesYesYes17.10.2016
Yes
Walking track work is started .
20Nellore0.5026.05.2016
Yes
YesYesYes17.06.2016
Yes
Filling work is in progress
21Tirupathi0.7517.08.2016
Yes
YesNoNo
22Chittoor0.5029.07.2016
Yes
YesYesYes23.09.2016
Yes
80% of kerbing work is completed, skating rink, Gazebo civil work under progress.
23Madanapalli0.5017.08.2016
Yes
YesYesYes31.08.2016
Yes
Civil work is under progress.
24Dharamavaram0.5002.10.2016
Yes
YesYesYes01.01.2017
Yes
Work is under progress, 25% completed.
25Guntakul0.5003.10.2016
Yes
YesYesYesNoProposed cancellation of the tender since market yard chairman has qualified in the bid. The commissioner placed cancellation order before the council and going for re-tender process.
26Kadapa0.2512.08.2016
Yes
YesYesYes24.09.2016
Yes
Marking completed, the Contractor was not responding and the Commissioner has issued notice to the contractor.
27Kadapa0.2512.08.2016
Yes
YesYesYes24.09.2016
Yes
Marking completed, the Contractor was not responding and the Commissioner has issued notice to the contractor.
28Kurnool0.5016.07.2016
Yes
YesYesYes03.08.2016
Yes
80% civil work completed.
29Adoni0.5029.10.2016
Yes
YesYesYes26.12.2016
Yes
Construction of compound wall is completed and filling works are under progress.
30Nandyala0.5028.07.2016
Yes
YesYesYes24.09.2016
Yes
Filling works is under progress.
31Ananthapuramu0.5002.06.2016
Yes
YesYesYes25.06.2016
Yes
Civil work is under progress (30% completed).
32Hindupur0.5006.10.2016
Yes
YesYesYes03.12.2016
Yes
Civil work is under progress (30% completed).
33Tadipatri0.5017.10.2016
Yes
YesYesYes06.12.2016
Yes
Works started 20% work completed.
34Proddutur0.5028.10.2016
Yes
YesYesNoNoTender opened and sent to C.E. office for opinion.

SAAP 2016-20 Projects

1. Water Supply Projects (2016-20)

S.No.ULB NameProject Cost
(In Cr.)
Tenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedRemarks
1Srikakulam5.5722.08.2017
Yes
YesYesNoNoG O issued
2Vizianagaram22.4019.06.2017
Yes
YesYesYesYesNoINFILTRATION WELL RCC WORK IS IN PROGRESS AND 600 DIA GALLERY PIPES AND 300 DIA DI PIPES ARE LAYING NELLIMARLA IN CHAMPAVATHI RIVER AND RAMATHEERDHALU IF WELL'S WORK IS IN PROGRESS. 2NOS ELSR RAFT CONCRETE IS COMPLETED. 500KL RESIVIVOR'S 1ST GROUND LEVEL BRACE CONCRETE IS COMPLECTED.
3GVMC75.1627.09.2017
Yes
YesYesYesYes18.11.2017
Yes
1000mm DI K7 procured quantity (5820 mts length), 800mm DI procured
Quantity (4575 mts length). 315mm HDPE 1.6kms, 160mm is 15.00kms, 200mm is 4.485kms pipes procured.
Work Progress :
HSC - 0/24,682 Nos.
D'system - 13301 / 36921 mts
Gravity main - 1000mm DI K7 pipes laying- 4652 /5820 mts.,
800mm DI K7 - 3460 / 4575 mts.
4Tadepalligudem58.3207.08.2017
Yes
YesYesYesYes13.11.2017
Yes
1.Designs are submitted at CE CDO Office for approval
2.No work progress due to SS Tank (Ac 9) land issue in the court
5Bhimavaram22.7507.08.2017
Yes
YesYesYesYes09.11.2017
Yes
LoA Issued.
Survey work in progress
6ELURU5.2320.06.2017
Yes
YesYesYesYes16.10.2017
Yes
As on date status:19-07-2018:- Eluru 16-20 W.S works : 400 dia DI K9 Pipes were (687.5Rmt ) arrived at site. &450 dia DI K9 Pipes(1430 Rmt )were arrived at site dated:29-12-2017.
(Inauguration Stone was kept by Local MLA at Kotthapet -ELSR Dated:06.02.2018- 9:00AM)
(Work was started Dated:21-02-2018 )-DI-K9-450 Dia .Laying -214.5 Rm Completed.
****************** WORK STOPPED BY AGENCY DUE TO PAYMENT ISSUE*************
1)DI-d/f-sluice valves(250,300,400 & 450dia ),DI-air valves ( 80 & 100 dia ) and DI-NRV-( 400 & 450 DIA ) Quality control Inspection was done (Dated:-18-05-2018 ).
7Machilipatnam22.7017.06.2017
Yes
YesYesYesYesNo
1. Site clearence work completed. (construction of 22 MLD Rapid Gravity Filtration plant-One-Job)
2 . Survey completed ( Laying of 800mm DI K7 of length 3450.)
3. Constitution of 325 KL capacity of Raw water Sump.
4. Constitution of Pump House (size 12.0X6.0m).
5. Filling with local avalable Sand work was completed. ( Filling with local avalable Sand for average depth of 1.0meter.)
6. Supply, delivery and Errection of 22 KW centrifugal Pump sets - 3 Nos.
7. Distribution net work with HDPE pipes - 22500 Rmt.
8. Restoration of Road with stone dust and M20 Concrete - 1484 Sqm.
9. Aretor( for 22 MLD WTP) work at ground level.
10. Flash mixture (for 22 MLD WTP) wall Reinforcement binding work is in progress.
11. 800mm DI K7 of Raw water Gravity Line pipes procured.
8Gudivada20.3525.07.2017
Yes
YesYesYesYesNoGO MS No 395 dated 10-11-2017 issued. LOA awaited.
9Guntur33.5313.12.2017
Yes
YesNoNoNo
Evalution of bids is in progress.
(Technical bid is opened ) Evalution of bids sent to Engineer-in-Chief for Technical opinion
10Narasaraopeta5.0825.07.2017
Yes
YesYesYes28.10.2017
Yes
Pipe line lining equipment set up work is in progress
Designs are in under process.
11Chilakaluripeta139.8025.05.2017
Yes
YesYesYesYes11.10.2017
Yes
1)Encasing Pipe of 1400mm Dia -18 no's(6mts length Each)procured.
2)7KM "MS" BARE Pipes Procured.
3)1200KL ELSR @ East-Malapalli:1st COLOMNS ABOVE 1ST BRACE IN PROGRESS{Stair case work in progress}
4)1200KL ELSR@Housing Board colony:1st brace above the ground level brace in progress{1st lift columns completed for stair case}
5)GRVITY LINE OF DIA 1100mm( MS PIPE LINE)-2337mts laid and work in progress,(GRAVITY LINE OF 1000mm Dia-2697mts laid & work in progress.
6)9MLD WTP- Aireator colomns completed,work in progress.
7)12mts dia sump-3rd lift side wall in progress.
8)Drawof well near existing ss-tank,earth work in progress.
12Ongole123.0018.07.2017
Yes
YesYesYesYes22.11.2017
Yes
Survey completed.
All ELSR and project related sites is been handed over byulb to pH office ongole.
Designs to be on approval..
Review meeting on Designs and progress with contractor is held at s.e pH office Nellore.
4.Designs is going to submit by agency today.5.Jungle clearance has completed by agency in One Elsr and WTP sites and ready for marking.
5.jungle clearance is going on at second ELSR site.6.Designs to be approved by SE office and works to be started shortly.
7.Approved designs has to come from SE a office.
Mean while Glbr approach road construction has started by IHP yesterday..
8.Some of the designs approved by SE office.
Approach road to Glbr location is going on.
Remaining works will start shortly.
7.Another Elsr site has marked by Revinue department and they are fixing boundaries today.
9.2nos of ELSR earth work excavation completed.
12.Glbr site excavation completed and ready for PCC.
13Nellore41.04NoNoNoNoThis project is proposed to be dropped as it is expected to be taken up by I&CAD dept.
14Nellore30.00NoNoNoNoAS accorded. TS awaited.
15Tirupathi55.1729.07.2017
Yes
YesYesYesYes12.11.2017
Yes
1) Pumping/Gravity Main-
I. 1100 mm dia MS pipe – Scope 8250 m Supply 0 m and laying 0 m, Hydro testing – 0 m

2) Feeder Main –
I. 250 mm dia DI K9 pipes – Scope 370 m Supply 368.50 and Laying 0 m, Hydro testing – 0 m
II. 300 mm dia DI K9 pipes – Scope 1200 m Supply 1199 and Laying 0 m, Hydro testing – 0 m
III. 400 mm dia DI K9 pipes – Scope 310 m Supply 310 and Laying 0 m, Hydro testing – 0 m

3) ELSR 3 no’s-
I. Madhav Nagar ELSR (1000 KL) – Annular raft work completed
II. Sriram Nagar Colony ELSR (750 KL) (Revised)– Raft slab completed.
III. Medical Collage ELSR (1200 KL) - soil testing.
4) Distribution network-
I. 110 mm dia HDPE pipe – Scope 25225 m Supply 23718 m and laying 7980 m, Hydro testing – 1378.42 m
II. 160 mm dia HDPE pipe - Scope 5347 m Supply 5191 m and laying 1635 m, Hydro testing – 0 m
III. 200 mm dia HDPE pipe - Scope 1982 m Supply 1037 m and laying 253.36 m, Hydro testing – 0 m
IV. 250 mm dia HDPE pipe - Scope 740 m Supply 625 m and laying 0 m, Hydro testing – 0 m
V. 300 mm dia DI K7 pipe - Scope 1075 m Supply 1072.5 m and laying 0 m, Hydro testing–0 m
VI. 400 mm dia DI K7 pipe - Scope 476 m Supply 474 m and laying 0 m, Hydro testing – 0 m

5) House Service Connections
I. HSC –Scope 5804 No’s-Procured 0 No’s -HSC completed -0 No’s
6) Payment released till date to the contractor- Nil
I.1st RA Bill submitted for a value of 2.58 crores.
II. Work completed till date for a value of 4.30 crores.
7) Issues-
I. QAP not yet submitted by the contractor for materials which are using at site
II. Laboratory not yet established by the contractor
16Chittoor250.0016.04.2018
Yes
YesNoNoTwo bidders participated. Bid evaluation in process.
17Madanapalli10.2417.07.2017
Yes
YesYesYes17.11.2017
Yes
LOA issued. Contract agreement concluded.Proposed land belongs to Revenue Department , ULB sent a letter to District Collector to handover the proposed land to ulb
18Dharamavaram11.1824.07.2017
Yes
YesYes15.02.2018
Yes
COT has Approved.
A legal letter from PH has been sent to the contractor to make an Agreement for the water supply project.

Physical Progress - Works yet to start.
1) HSC's (Nos) - Scope - 7160 nos. QAP yet to be submitted for approval & material procurement.
2) Distribution Network - Scope - 23000 m. QAP yet to be submitted for approval & material procurement.
3) Transmission Main - Scope - 2000 m, QAP yet to be submitted for approval & material procurement.
19Guntakul10.9809.10.2017
Yes
YesYesNoAgreement is pending.
LOA Date: 16-02-2018.
20Kadapa67.7326.08.2017
Yes
YesYesYesYes24.11.2017
Yes
1. Improvement of Lingampalli Head Water Works Ground water investigation report received from Ground Water and Water Audit department. Designs
under preparation
2. Hydraulic designs and drawings of Gravity mains from GLBR at Bandikanuma Hillock to ELSRs are at the stage of approval.
3. Hydraulic designs and drawings of Distribution network in Kadapa town is yet to be furnished by the agency
4. The Designs & drawings of 4 ELSRs @ Utukuru, Prakash Nagar, Masapet, Telugu Ganga Colony are at the stage of approval
21Kurnool43.94NoNoNoNoNIT to be floated
22Adoni23.5818.07.2017
Yes
YesYesYesYes24.11.2017
Yes
1)G.O. No. 386 issued on 06.11.2017.
2) Survey completed on 08.12.2017.
3) Soil investigation completed on 12.12.2017.
4) Hydraulic designs submit through mail on 17.01.2018
5) ELSR Structural Designs submit through mail on 19.01.2018.
6) Joint inspection with Ph QC EE, Ph AE at srikalahasthi pipes factory for 600mm DI pipe line on 25.01.2018.
7) Inspected 600mm DI K9 pipes received 396mts to basapuram on 28.01.2018.
8) 600mm DI K9 pipes received 648mts to basapuram on 29.01.2018.
9) 600mm DI K9 pipes received 660mts to basapuram on 30.01.2018.
10) 600mm DI K9 pipes received 264mts to basapuram on 31.01.2018. total received 1967 mts.
11)As per Ph SE & DEE sir instruction, contractor take 5 soil sample at basapuram to ramjala raw water transmission pipe lines to send lad and to know characteristics of soil due to corrosions on old DI pipes on 02.02.2018.
12) ELSR's structural designs approved.
13) LS of 600mm & 300mm DI pipes for raw water transmission approved.
14)On 12.03.2018 Work started at ramjala to yemmiganuru road Pipe line 300mm DI K7 & 1000KL ELSR excavation started at ramjala,
15) On 16.03.2018 earth excavation completed at Ramjala for 1000KL ELSR,
16) Earth work starts at raitu bazar for 1000KL ELSR construction on 23.03.2018.
17)Excavating & laying 300mm DI K7 pipe line- 680 mts completed at ramjala,
18)WTP structural designs yet to be submit.
23Nandyala137.3416.06.2017
Yes
YesYesYesYes25.07.2017
Yes
1. Contract Agreement completed
2. Survey work completed, design in progress.
3.Di pipe Gravity main 900 K7 3030 Mtrs laid ( Total qty 3750 Mtrs )
800 K7 84 mtrs laid ( Total qty 250 Mtrs )
600 K7 402 Mtrs laid ( Total qty 680 Mtrs )
4. Raw water main MS pipe 1100 Dia 2514.20 Mtrs laid ( Total qty 31130 Mtrs )
5. Elbr 200 kl G+1 brace beam bar bending work in progress
6. Clear water sump 1000 Kl raft bar bending work raft completed .
7. Clariflocculator 1 Pcc completed
8. Clariflocculator 2 excavation in progress
9. Chemical house Excavation completed.
24Ananthapuramu15.3526.08.2017
Yes
YesYesYesYes25.10.2017
Yes
1) Agreement Concluded.
2) Survey work completed
3) WTP location - Soil investigation completed
25Hindupur194.0031.08.2017
Yes
YesYesYesYes15.09.2017
Yes
Contract Awarded to M/s. KLSR Infratech Ltd
26Tadipatri145.1422.11.2017
Yes
YesYesYesYes28.02.2018
Yes
LOA dated 28.02.2018 issued, Agreement to be concluded. Water allocation GO is awaited.
27Proddutur151.3817.06.2017
Yes
YesYesYesYes24.11.2017
Yes
Agreement Concluded on 28.12.2017

PRODDATUR -AMRUT SAAP 2106-2020

Intake well & GLBR :
Designs not received yet

WTP & ELBR :
Soil sample taken on 05.01.2018.Designs yet to prepare.Site handover pending.

Forest department permissions for clearing of trees .

APSPDL Shifting of Electrical line & Transformers .

ELSR 1 : Site changed due to Chairperson instructions on 20.01.2018 .

Site changed from Bollavaram to Hanuman Nagar - Soil sample taken on 13.02.2018.Site handover pending.

ELSR 2 : Site changed from Modempalle to Bharat function hall back side site , Yerraguntla road.

While on jungle Clarence deadbodies came ..Work stopped and site changed from Bharat function hall back side to Veterinary hospital site...Site handover pending.

ELSR 3 : Site changed from Rameswaram to Municipal park ..Soil sample is taken for lab reports.Site handover pending.

Soil sample collection completed at
ELSR -1 Municipal Park,
ELSR -2 ARTS College,
ELSR -3 Veterinary Hospital
by Sri Venkateswara University,Tirupathi. Lab report is pending.

ELSR-2 : ARTS college site handover is pending,
ELSR-3: Veternaty Hospital site handover is in progress.

On 26.02.2018

Letter addressed to Managing Director, State veterinary department from Proddatur municipality for asking permission to construct ELSR on Veterinary department site.

Level Section ,WTP, Intake Well Hydraulic drawings sent to SE(PH) by contractor .Waiting for structural drawings.
On 06.03.2018
Permissions received from AE (APSPCDL) for shifting if Electrical lines,Transformers at Rameswaram Head Water Works,Proddatur.
WTP,SBC reports received from Pullareddy Engineering College,Kurnool
WTP Structural drawings submitted to SE (PH),Anantapur
SE(PH) sir suggested some changes (level Section) in WTP to Contractor MEGHA Engineering & Infrastructure Ltd,Structural drawings for ELBR,Pump house is pending.

After making corrections WTP Structural drawings submitted 2nd time to SE (PH),Anantapur.

Municipal Park ELSR site handling over document with site plan submitted from Proddatur Municipality to Executive Engineer,Kadapa

Water supply pipeline Railway crossing application is at South Central Railway division office,Secundrabad

Corrections for Level Section drawings approved by SE (PH) , Anantapur

WTP structural drawings Scrutining is ongoing at Se (PH) office ,Anantapur

ELSR's Structural drawings submitted & Scrutining is ongoing at SE (PH),Anantapur

"Soil sample collection completed for WTP,Pumphouse,Calriflocator,GLBR,Filtration wells
by Sri Venkateswara University,Tirupathi."

On 24.03.2018
Survey work started for feeder main from Rameswaram water head works to ELSR's, Locations (Gandhi municipal park,Arts college,Veterinary college, Nadimpalle, Old market),Feeder main survey completed, Levels & Length submition to SE (PH),Anantapur is pending

For Intake well,GLBR,Pipeline along the North canal permissions approved by Irrigation dept,Under taking letter from PH dept (or) Contractor (for total project completion period) to Irrigation dept is pending

DI pipe QAP approved by SE(PH), Anantapur and hard copy forwarded to EE (PH) ,Kadapa & Megha Engineering & Infrastructure Ltd .

Undertaking letter submitted for (Irrigation land at Mylavaram for GLBR,Intake well & Pipe line along Mylavaram north canal ) irrigation dept properties from Megha Engineering & Infrastructure Ltd to DyEE (PH), Proddatur
and forwarded it from DyEE to EE Irrigation dept,Kadapa

For ELSR-3 at veterinary hospital site, land approval letter received from Director of animal husbandry,Vijayawada

WTP, ELSR's, ELBR, GLBR, Intake Well Structural drawings & Designs not approved yet by SE(PH).

ELSR's (3 No's) Structural Drawings & Designs approved by SE(PH), Anantapur .

Requesting letter with Sketch for land handing over forwarded from Municipal Commissioner to Director of Animal Husbandry department, Vijayawada.

ELSR's (3 No's) Structural Drawings & Designs received to DyEE (PH), Proddatur .

Steel procured for ELSR-3 at Municipal park JSW neo FE 500D 10 mm,16 mm.Waiting for steel lab test reports.

On 25.04.2018 water supply scheme 2016-20 Bhoomi pooja completed at ELSR-3 at municipal park site Proddatur in the presence of Chairperson Sir,Commissioner sir,Ward councilor ,DyEE(PH), AEE , AE, CMMU Staff

Excavation work started at ELSR-3 at municipal park site Proddatur

Work stopped in municipal park ELSR due to political involvement

Waiting for Veterinary hospital site ,Irrigation Dept site, RDC nandyala permissions

Waiting for WTP,Intake well structural drawings approval from SE(PH), Anantapur

QAP industrial inspection finalized for DI K7 900 dia pipes on 07.05.2018 to Srikalahasti Pipes Ltd at Rachagunneri village,srikalahasti mandal,Chittoor District,
Andhra pradesh.

QAP for DI specials submitted to SE(PH),Anantapur

On 07.05.2018 QAP industrial inspection completed along with EE(QC), DyEE(PH), AEE(QC), Megha engineers for the quantity 1998 mts (333 No's) of DI K7 900 dia pipes at Srikalahasti pipes ltd.

Mix designs(Penna Cement M15, M20, M25, M30 - Ramco Cement M15, M20, M25, M30 - Coramandal cenemt M30 - Dalmia M30) , Sieve analysis submitted for approval to SE(PH)

QAP industrial inspection finalized for DI Specials on 16.05.2018 to Electrosteel Castings Ltd at Kolkata

DI K7 900 dia pipes unloading going at railway station road ,near by rameswaram water head works 1998 mts (333 No's)

On 16-05-2018 Industrial inspection completed along with DyEE (PH),AEE (QC) for DI K(12 &13) 900 dia fittings 30 no's (Bends-11.25°,21.5°,45°,90°,Collars,Flanges) at Electrosteel Castings Ltd, Kolkata.

Excavation work completed at ELSR-3 at municipal park site Proddatur ,Dressing work & Sand bedding work is going on.
Shuttering work satarted for PCC at Municipal park site,Proddatur
PCC work completed for ELSR-3 at Municipal park site,Proddatur
Bar bending work started for foundation annular raft ELSR-3 at Municipal park site,Proddatur
Column marking work started for foundation annular raft ELSR-3 at Municipal park site,Proddatur

Reinforcement work started for foundation annular raft ELSR-3 at Municipal park site,Proddatur

QAP industrial inspection 2nd time finalized for DI Specials (39 No's) on 19.06.2018 to Electrosteel Castings Ltd at Kolkata
28Kavali59.3011.09.2017
Yes
YesYesYesYes24.11.2017
Yes
G.O No. 396 dt 10.11.2017 issued. LOA issued on 24.11.2017. Agreement done at SE(PH) Nellore awaiting for details
29Srikalhasthi5.2416.04.2018
Yes
YesNoNoBid opened, 2 bidders participated. Evaluation in progress.

2. Sewage & Septage Projects (2016-20)

S.No.ULB NameProject Cost
(In Cr.)
Tenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedRemarks
1Srikakulam28.4426.09.2017
Yes
YesNoYesYes19.12.2017
Yes
Designs submitted,
2Vizianagaram19.9226.09.2017
Yes
NoNoYesNoGRAVEL FILLING IN DRAIN WORK COMPLETED. WORK YET TO BE STARTED
3GVMC33.3129.09.2017
Yes
YesYesYesYes26.12.2017
Yes
HSC’s pipes
18kms length pipes and Manhole covers - 75 nos. arrived at site, HSC’s Surveying in progress at Zone 3 & 4. Excavation and 110mm dia pipe laying in progress for HSC work in Vepagunta zone 6 and Gopalapatnam, Kakani nagar and madurawada in Zone 4.
Components :
UGD HSC - 1000 / 27,841 Nos.
4Rajahmundry17.9826.09.2017
Yes
YesNoYesNoG.O Issued. LOA to be issued.
5Kakinada29.1726.09.2017
Yes
YesYesYes22.12.2017
Yes
Design and
Drawings submitted.
6Tadepalligudem32.1426.09.2017
Yes
YesYesYesYes20.12.2017
Yes
Status:Survey work is in progress for Gravity main
Issues:No work progress due to Land alienation of STP Site
7Bhimavaram15.7026.09.2017
Yes
YesNoYes20.12.2017
Yes
G.O issued.
LOA Issued.
8ELURU37.4826.09.2017
Yes
YesNo20.12.2017
Yes
As on date Status:19-07-2018:-
STP - Soil Investigations and (Dated:10.01.2018) in Eluru town at STP location..
UGD-Survey works & STP site cleaning work had done. EPC-Design work under progress, Bhoomi pooja completed ( 25.04.2018 ) By MLA,MP & MUNICIPAL MYAIOR,
1).Admin Building columns casting up to Plinth beam bottom was completed. And BACK FILLING is going on.
2)SBR-PCC for Raft and Base slab concrete completed ..*********
3)SBR-SS Pump pit raft concrete(M30) was done (27.06.2018 )*******
3A) MANHOLE-COVERS-QAP-INSPECTION at Guntur. along with PHED-Dy.EE,QC- was done .(05-07-2018 )*******
4)SBR-W1 wall wes side raft concrete (M30 ) was completed (13-07-2018 ).******
5)GUARD ROOM Roof slab casting completed. Brick work under progress**
6)SBR-W2 wall raft reinforcement work under progress.******
9Vijayawada39.8824.10.2017
Yes
YesYesYesYes08.02.2018
Yes
1.Sewerage pumping station curb wall shuttering work completed ready for concrete in APIIC Colony in ward no-2
2.Factory insepction for DI pipes (dia 250,500&600mm )along with DEE Rashmi Metalics Ltd in Kharagpur
10Machilipatnam16.7627.09.2017
Yes
NoNoYesNo
1 . Jungle clearence and Survey work completed.
and Soil testing is in progress. Investigation Survey by Total Stastion - 1 - Job.
2. Diversion works with RCC M 30 - 1 - Job.
3. Designing and constitution of Inlet works, Screen Chamber, Grit Chamber, Wet Well 8.5 Dia and 9m depth.
4. Errection of submersible Pumps - 2 Nos.
11Gudivada16.7627.09.2017
Yes
YesYesYesYesNoG.O Ms No 445 dated 18-12-2017 issued. LOA awaited.
12Tenali30.0627.09.2017
Yes
NoNoYesNoG.O issued. LOA to be issued.
13Chilakaluripeta16.7627.09.2017
Yes
NoNoNoTender Floated on 27.09.2017. Last date for submission is 24.10.2017.
14Ongole30.7926.09.2017
Yes
YesYesYesYes20.12.2017
Yes
1. LOA issued on 20.12.2017.
2. Agreement concluded on Jan 11th 2018.
3. Today 30-1-2018 there is a meeting held at Nellore pH office in between contractors and s.e pH sir regarding progress.
4.STP site boundaries is going to mark by Town Planning department tomorrow and designs is going to submit by agency on 7th of February.
5.Surveyer of townplanning department of ulb has to fix the boundaries, may be on coming Monday the total process of site handing over is to be completed from ulb to pH office.8.site has to be marked by MRO surveyor.
Works to be started shortly.
7.proposal site has to be handover by MRO of Revinue department to pH office.
Work to be started shortly.
8.Revinue department surveyor has to fix boundaries and has to handover the site to pH department soon.Then work will start immediately because agency is ready with all ground work preparations.
9.still Revinue department has not handed over the site to pH department and waiting for their Surveyor to mark the site.
10.site acquisition is in process for STP land...
15Tirupathi59.0516.11.2017
Yes
YesYesYesYes27.02.2018
Yes
1. Survey work completed
2. designs has to submitted by the contractor for scrutiny
16Chittoor33.39NoNoNoNoIt is proposed in 8th SLTC to delete this project and transfer the funds to Chittoor WS project under SAAP 2016-20.
17Madanapalli15.9526.09.2017
Yes
YesYesYesYes15.12.2017
Yes
Go 433, dated 15.12.2017.,1.Agreement concluded Works to be started, CR Awarded, ULB Proposed STP Land Handovered to Public Health works to be expedited.
18Dharamavaram48.1725.09.2017
Yes
YesYesYesYes22.12.2017
Yes
Met PH DEE sir and discussed the STP Land details. The Soil sample test Report will be coming in 2 days.
Waste water has been collected at the Intercepting point and sent to the lab for testing.
An Access road has made by the contractor to the Site.
Layout Designs and Drawing are submitted to S.E office.They are under Scrutiny by Public Health Dept.
19Guntakul26.7125.09.2017
Yes
YesYesYesYes22.12.2017
Yes
Agreement to be concluded.
Contract Agreement Date:07-02-2018.
Work not started due to Land acqusition issue.
Letter issued from RDO office to GMC Commissioner regarding Deposite of Cost of Land Acqusition requested.Date:20-01-2018
Letter No: RC.NO.D1-LA/2814/2017.
STP Deposite of Cost of Land Acqusition requested CR is approved in a Council meeting. Date:30-04-2018.
CR NO:205.
20Kadapa94.3501.03.2018
Yes
YesNoNo1) 20 MLD STP price bid had opened in SE (PH) office. Awaiting for G.O
2) 30000 House service connections - 7th time NIT floated. Last date for BID submission 21.05.2018
21Kurnool47.9330.09.2017
Yes
YesYesYesYes18.01.2018
Yes
Agreement to be concluded.
22Adoni15.8425.09.2017
Yes
YesYesYesYes30.12.2017
Yes
1)Agreement concluded on 31/01/2018.
2)Land Acquisition revised from 4 acres to 2 acres after discussion with ULB & PH Dept.
3)Block levels completed for construction of 5 MLD STP at rayanagar on 07.03.2018,
4)Drain sample collected at rayanagar & sent lab for reports on 13.03.2018,
5)land acquisition in progress

23Nandyala33.4725.09.2017
Yes
YesYesYesYes27.12.2017
Yes
GO issued on 27.12.2017. LOA to be issued.
24Ananthapuramu29.7625.09.2017
Yes
YesYesYesYes22.12.2017
Yes
Agreement date 02.02.2018
25Kavali29.1126.09.2017
Yes
YesYesYesYes15.12.2017
Yes
GO 430 dated 15.12.2017. LOA issued.Agreement done at SE(PH),awaiting for details.
26Srikalhasthi26.8525.09.2017
Yes
YesYesYesYes15.12.2017
Yes
Agreement concluded on 12.01.2018.

3. Storm Water Drainage Projects (2016-20)

S.No.ULB NameProject Cost
(In Cr.)
Tenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedRemarks
1Srikakulam40.0219.08.2017
Yes
NoNoNoSurvey work is in progress
2Rajahmundry82.1616.09.2017
Yes
YesNoNoTwo bidders participation, Technical Bid Evaluation Under Progress.
3Kakinada91.4816.09.2017
Yes
YesYesYes28.03.2018
Yes
Survey work completed, Drawings submitted.
4Machilipatnam21.5128.08.2017
Yes
YesNoYes06.12.2017
Yes
Contractor Survey work completed .
1. Construction of primary Drains with VRCC M 20 - 4109 Rmt.
2. Construction of Secondary Drains with VRCC M 20 - 5676 Rmt.
3. Construction of Tertiary Drains with VRCC M 20 - 987 Rmt.
4. Construction of existing Drain gaps with VRCC M 20 - 1651 Rmt.
5Nellore82.0223.01.2018
Yes
YesYesYesYes21.06.2018
Yes
GO no. 107 dated 20.03.2018 issued. LOA to be issued.
6Tirupathi12.1930.01.2018
Yes
YesYesYesYes18.04.2018
Yes
1.LOA issued on 18.04.2018. Agreement to be concluded.
2. Survey work completed
3. Designs has to submitted by the contractor for scrutiny
7Ananthapuramu21.3717.03.2018
Yes
YesNoNoOne bidder participated. Evaluation under progress.

4. Parks & Green Spaces Projects (2016-20)

S.No.ULB NameProject Cost
(In Cr.)
Tenders FloatedTenders ReceivedTenders EvaluatedCOT ApprovedCOM II ApprovedGO IssuedAwardedRemarks
1Srikakulam3.4503.07.2017
Yes
YesYesYes26.07.2017
Yes
Agreement concluded and works are under progress
2Vizianagaram1.4403.07.2017
Yes
YesYesYes24.07.2017
Yes
Agreement concluded and works are under progress
3GVMC2.2408.06.2017
Yes
YesNo26.08.2017
Yes
Agreement concluded and works are under progress
4Rajahmundry1.9203.08.2017
Yes
YesYes20.11.2017
Yes
5Kakinada1.0501.06.2017
Yes
YesYesYes27.07.2017
Yes
Agreement concluded and works are under progress
6Tadepalligudem1.0208.06.2017
Yes
YesYesYes25.07.2017
Yes
Agreement concluded and works are under progress
7Bhimavaram0.8901.06.2017
Yes
YesYesYesNoAgreement to be concluded with Bhimavaram Municipality
8ELURU1.1901.06.2017
Yes
YesYesYes01.08.2017
Yes
Agreement concluded and works are under progress
9Vijayawada1.7503.08.2017
Yes
YesNoNoTenders are under evaluation
10Machilipatnam1.0017.05.2017
Yes
YesYesYesNoAgreement not yet concluded due to change in the location of the park by the Machilipatnam Municipality
11Gudivada0.8217.05.2017
Yes
YesYesYes07.06.2017
Yes
Works are under progress
12Tenali0.8301.06.2017
Yes
YesYesYesNoAgreement yet to be concluded with the Tenali Municipality
13Guntur1.2601.06.2017
Yes
YesYesYesNoAgreement yet to be concluded with Guntur Municipal Corporation
14Narasaraopeta0.7430.10.2017
Yes
YesYesYes14.11.2017
Yes
Agreement yet to be conluded
15Chilakaluripeta1.0717.05.2017
Yes
YesYesYes24.07.2017
Yes
Agreements are concluded and works are under progress
16Ongole0.6717.05.2017
Yes
YesYesYes07.06.2017
Yes
Agreement concluded, works are under progress
17Nellore1.1117.05.2017
Yes
YesYesYes07.06.2017
Yes
Agreements concluded and works are under progress
18Tirupathi0.9717.05.2017
Yes
YesYesYes07.06.2017
Yes
Agreement concluded and works are under progress
19Chittoor1.2903.07.2017
Yes
YesYesYes24.07.2017
Yes
Agreement concluded and works are under progress
20Madanapalli0.7403.08.2017
Yes
NoNoNotwo tenderers have participated and got disqualified and it is proposed to recall the tender
21Dharamavaram1.1003.08.2017
Yes
NoNoNoNo tenderers have participated in this tender and it is proposed to recall the tender.
22Guntakul0.6601.06.2017
Yes
YesYesYes27.07.2017
Yes
Agreement concluded and works yet to be started
23Kadapa1.2317.05.2017
Yes
YesYes07.06.2017
Yes
Agreement concluded and works yet to be started
24Kurnool1.2617.05.2017
Yes
YesYesYes07.06.2017
Yes
Agreement concluded and works are under progress
25Adoni0.7208.06.2017
Yes
YesYesYes01.07.2017
Yes
Agreement concluded, works yet to be started
26Nandyala0.9517.05.2017
Yes
YesYesYes07.06.2017
Yes
Agreement concluded, works are under progress
27Ananthapuramu0.7701.06.2017
Yes
YesNoYes01.07.2017
Yes
Agreement concluded and works yet to be started
28Hindupur0.6101.06.2017
Yes
YesYesYesNoAgreement yet to be concluded with the Hindupur Municipality
29Tadipatri0.67NoNoNoNoLocation is not finalised from Tadipatri Municipality
30Proddutur0.9108.06.2017
Yes
YesYesYes07.06.2017
Yes
Agreement concluded and works are under progress
31Kavali1.2108.06.2017
Yes
YesYesYes01.07.2017
Yes
Agreement concluded and works are under progress
32Srikalhasthi1.0724.07.2017
Yes
YesYesYes28.08.2017
Yes
Agreement concluded and works yet to be started

SAAP 2017-20 PROJECTS AT A GLANCE

S.No.SectorNo. of ProjectsSAAP Approved Cost (Cr.)SLTC ApprovedAS AccordedTS AccordedTenders FloatedAwarded
1Parks & Green Spaces3231.8511000
StatusRemarks / Comments
DPR Design Stage (31): Vizianagaram,GVMC,Rajahmundry,Kakinada,Tadepalligudem,Bhimavaram,ELURU,Vijayawada,Machilipatnam,Gudivada,
Tenali,Guntur,Narasaraopeta,Chilakaluripeta,Ongole,Nellore,Tirupathi,Chittoor,Madanapalli,Dharamavaram,
Guntakul,Kadapa,Kurnool,Adoni,Nandyala,Ananthapuramu,Hindupur,Tadipatri,Proddutur,Kavali,
Srikalhasthi
Administrative Sanction (AS) Accorded (1): Srikakulam



Total3231.8511000

SAAP 2017-20 Projects

1. Parks & Green Spaces DPRs (2017-20)

S.No.Name of ULBSAAP Project Cost (Cr.)SLTC ApprovalAdministrative Sanction
(GO)
DPR Submitted for TSTS AccordedRemarks
NoDateApproved Cost (Cr.)NoDate
1Srikakulam0.87408.03.201711628.03.2017DPR prepared under SAAP 2016-17 project for entire mission period.
2Vizianagaram0.87DPR submission due
3GVMC2.09DPR submission due
4Rajahmundry0.87DPR submission due
5Kakinada1.31DPR submission due
6Tadepalligudem0.87DPR submission due
7Bhimavaram0.87DPR submission due
8ELURU0.87DPR submission due
9Vijayawada2.09DPR submission due
10Machilipatnam0.87DPR submission due
11Gudivada0.87DPR submission due
12Tenali0.87DPR submission due
13Guntur1.31DPR submission due
14Narasaraopeta0.87DPR submission due
15Chilakaluripeta0.87DPR submission due
16Ongole0.87DPR submission due
17Nellore1.10DPR submission due
18Tirupathi1.10DPR submission due
19Chittoor0.87DPR submission due
20Madanapalli0.87DPR submission due
21Dharamavaram0.87DPR submission due
22Guntakul0.87DPR submission due
23Kadapa0.87DPR submission due
24Kurnool1.10DPR submission due
25Adoni0.87DPR submission due
26Nandyala0.87DPR submission due
27Ananthapuramu0.87DPR submission due
28Hindupur0.87DPR submission due
29Tadipatri0.87DPR submission due
30Proddutur0.87DPR submission due
31Kavali0.87DPR submission due
32Srikalhasthi0.87DPR submission due